Client: Midlands Precision Components Ltd
Location: Tyseley Industrial Estate, Birmingham
Scope: HV grid connection for a 24/7 automotive parts manufacturing facility
Overview
Midlands Precision Components operates a high-throughput facility producing drivetrain components for Tier 1 automotive suppliers. With rising energy demands and plans to electrify key processes, the client required a robust, scalable grid connection to support future growth and sustainability goals.
TriEnergi Power Solutions was appointed to deliver a contestable HV grid connection under ICP accreditation, ensuring speed, cost-efficiency and full compliance with ENA G99/G100 standards.
Scope of Works
Grid Connection Design
- 1MVA HV supply via 11kV connection
- ENA G99 compliance study and PGMD documentation
- Fault-level and harmonic analysis using DigSILENT PowerFactory
Civil & Electrical Works
- HV cable trenching (1.2 km) with traffic management
- Installation of RMU, transformer (1MVA), and metering
- Earthing system and surge protection
DNO Liaison & Approvals
- Coordination with Western Power Distribution
- Achieved connection offer acceptance in 4 weeks
- Grid code compliance verified pre-commissioning
Our Client Review
TriEnergi’s ICP-led approach gave us speed, savings and peace of mind. Their technical team navigated grid compliance with precision, and the installation was seamless. We’re now exploring solar and storage integration for phase two.
James Holloway, Facilities Manager, Midlands Precision Components Ltd